COMPLETE
CATEGORY: ENABLING CONNECTIONS
Embedded Capacity Register (ECR)

What we will do and why
The Embedded Capacity Register (ECR) has been developed to provide enhanced information on Distributed Energy Resources (DER) and network requirements.
Key deliverables
- Provide information on generation and storage resources (>50kW) that are connected, or accepted to connect, to our network.
- Include information on flexibility services that are being provided by connected resources.
- Include details of reinforcement for “accepted to connect” projects where appropriate.
Target outcomes
- Open and accessible.
- High levels of data accuracy and completeness.
- Updated on a monthly basis.
Measures of success
- Percentage completeness of key fields.
- High levels of customer satisfaction.
Planned start:
01.12.2021
Target completion:
31.12.2023
Key milestones:
- Technical specification
- Customer consultation
- User acceptance testing
- >1MW register published
- >50kW register published
Status:
Complete