IN FLIGHT
CATEGORY: ENABLING CONNECTIONS
Self-serve curtailment studies

What we will do and why
Provide customers with data sets and ‘how to’ guides to enable them to complete their own curtailment studies for projects where a DERMS solution is required.
Key deliverables
- Online data sets.
- Online training material.
Target outcomes
- Improved accuracy of curtailment studies.
- Customers better able to make informed decisions about the viability of their connection project.
Measures of success
- High levels of customer satisfaction.
- Volume of customers projects connected.
Planned start:
01.04.2023
Target completion:
31.12.2024
Key milestones:
- Customer engagement
- Training material
- Data production
- Publication on Open Data Portal
- Go-live
Status:
On track
Date of change | Reason | Description |
---|---|---|
03.10.2024 | Revised completion date |
Due to high interest, we have expanded the number of customers we are testing this with and are allowing further time for them to do so |