IN FLIGHT

CATEGORY: ENABLING CONNECTIONS

ENA Fleet Decarbonisation Guide

electric-vehicle-charging

What we will do and why

Fleet Operators and their Trade bodies have told us that they find it hard to navigate the connections processes of different DNOs. Their needs differ depending on the size, type and maturity of the Fleet Operator. Working with the ENA, other DNOs, Operators and the transport sector, we will enable any fleet to find the right support for their organisation.

Key deliverables

  • Digital tool that both informs and advises Fleet Operators on their next best step to getting connected.

Target outcomes

  • Any Fleet Operator able to use the tool to support with their fleet electrification.

Measures of success

  • High levels of customer satisfaction obtained during testing & through the Major Connections Customer Satisfaction Survey (MCCSS).

Planned start:

01.06.2024

Target completion:

30.09.2025

Key milestones:

  • Requirement gathering
  • Customer journeys developed
  • Digital Design developed
  • Customer testing
  • Digital toolkit launch

Status:

In progress